Abuja-Kaduna rail line 85% complete, says Minister




Whatsapp News

DOKA –   Minister Transport, Sen. Idris Umar, said on Saturday that - Gauge Rail Modernisation was 85 per cent completed.

Umar announced this in Doko, at a ceremony mark attainment 100km track-laying for railway modernisation .

Vice Namadi Sambo, launched the track-laying at Idu, , in July 2013.

“Today, in less than one year, the construction has attained over 100km out 186km. In the next three months, the track will be completed.

“All the materials required are already on ground achieve the completion and availability of the rail line’’, he said.

He said the major constraints encountered in the construction were in and had been overcome.

He said the constraints of water interference at kilometre 19 and some  estates built along the rail line in Kubwa were resolved.

Umar urged the Chinese Civil Engineering Construction Company (CCECC) handling the continue with the zeal and determination with which they started.

Mr James Li, Project Manager, CCECC, said there had been steady in the construction of the rail line since the commencement of the track-laying.

He said earthwork site clearing had been done and devoid of obstructions or existing structures; while cutting, including rock blasting and filling were at advanced stages.

“About 185 km of the 186.5km route distance has been cleared, 8,597,000m of earth excavated, 403,000m of rock blasted and 6,064,000m of earth filling done.

“Sub structural works have now been completed on all the 26 railway bridges while all the five box bridges have also been fully completed.

“Also 13 out of than 30 over-pass bridges have been completed while work is in on 16 others’’, Li said.

He said construction has started on 203 out of the scheduled 206 railway culverts while preparation work was in for the commencement of remaining three culverts.

He said than 330,000 pieces of concrete sleepers had been pre-cast while the required 348 pieces of pre-cast T-beams had been produced.

Li noted that the track laying had reached advanced stage of 110km of track panel laid and 47,356m ballast distributed.

According to the project manager, work has started fully on the seven of the required nine station buildings. (NAN)